PROJECT
TEAM (TCA Members):

MBT Architecture, San Franciso, California
Structural Engineers Inc, Los Altos,
California
SIZE: 294,000 sq.ft.
TOTAL COST: Confidential
Tallest Panel:
33-ft Comp. Cost: Confidential
Largest Panel: N.R.
Shell Const: 355 days
Heaviest Panel: 135,000 lbs.
Was Owner Familiar with Tilt-Up? Yes
Why Did the Owner Select Tilt-Up?
Although it was not the owner's original intent to use Tilt-Up, they were persuaded by the architect, MBT Architecture, to use it as a cost-saving method of building and were extremely pleased with the completed project.
What was the Project Mission?
To create an aesthetically pleasing
building that is cohesive to the site context of Stanford Research Park,
while meeting the schedule and cost constraints.
What were the special architectural treatments?
The color schemes of the buildings are meant to be in harmony with the Stanford Research Park and with the city of Palo Alto. Aluminum specialty details give the building a more sophisticated feeling.
What were the outstanding features?
In order to lighten the appearance of the buildings, the panels were pulled back at the corners, allowing glass windows to be inserted. An arcing, pedestrian-scaled entry drive accentuated with special paving finishes, and punctuated with lavishly landscaped entry courts is the main organizing element of the site.
What special materials were used?
Fly ash use in all the concrete for the project is raised significantly from current industry standard 14%, between 20% and 30% in over half the concrete on the project. Fly ash, as a substitute for Portland cement in concrete, provides substantial environmental benefits, both through the recycled use of the ash created in manufacturing and waste incineration, as well as in reducing production of Portland cement, a recognized environmental hazard. Fly ash ranging from 14% to up to 50% results in an average of nearly 30% fly-ash use overall.
What was the
Overall Complexity of the project? This was
an extremely complex project for a variety of
reasons.

This project consists of the redevelopment of a
16.3-acre parcel in the Stanford Research Park.
TIBCO Software is the tenant in the
redevelopment.
The site is a long irregularly shaped parcel
with three existing large single-story
structures and several chemical storage
outbuildings. The existing buildings have been
demolished and replaced by four new buildings.
The buildings are a combination of one and two
stories, totaling approximately 294,000 s.f. The
development of the design required tight cost
control from the earliest design phase through
construction. Value Engineering was viewed as an
ongoing process through completion, and the
project was built well below budget.
First, there were many site constraints. There
were several ground water evacuation wells
distributed throughout the site. Along with
environmental clean-up issues, the buildings had
to be placed on the site in such a way that they
were not in the way of these wells.
Sustainability Issues were also a factor in the
success of this project.
Sustainable design issues were addressed
successfully in a politically sensitive and
contentious environment. The incorporation of a
"green building" program, including specialized
glazing, sun shades, high thermal mass materials
and light-colored and recyclable roofing
materials met the stringent requirements of the
Palo Alto Architectural Review Board.
A 100 ft. wide landscape zone at Barron Park and
an estimated 37 ft. wide buffer zone along
Matadero Creek, presented an opportunity to
incorporate extensive landscaping, bioswale
filtration, riparian vegetation and a five ft.
wide pedestrian path along most of the creekside.
Preservation of the creek riparian environment
was addressed as a specialized project under the
direction of a riparian habitat specialist. In
addition, a vegetated berm provides visual and
acoustical separation between the project and
Barron Park residential neighborhood.
Successfully meeting Palo Alto permits and
requirements was another challenge for the
design team.
All work in Palo Alto affecting exterior
appearance in any way requires Architectural
Review Board (ARB) submittal. The additional
submittal for "Preliminary ARB" is optional, but
usually results in a more timely outcome. Many
recent MBT projects that have been presented to
the ARB are within the Stanford Research Park.
There is an additional requirement for all work
performed in the Stanford Research Park, whether
exterior or interior improvements, that they be
submitted for Stanford Management Company review
and approval. This process generally takes two
to three weeks.
As with any developer building, meeting the
budget is always a main challenge. Specifically
for this project, the budget required a
completion at 50% less than the typical
developer budget. This challenge was met by the
decision to use tilt-up as the construction
method. Also, the panels used an admixture that
optimized drying time and helped to keep the
project on schedule.
However, as this challenge was met, another one
arose. The owner still wanted an elegant
building with architectural richness. The design
team implemented creative use of structural
engineering to allow for more window openings in
the building and thus avoid a "heavy" feeling
that is usually associated with tilt-up panels.
The design of the building incorporates bands
between each panel to make-up for
irregularities. There was also the use of
aggressive sand blasting to the panels to create
a richness of texture. Aluminum specialty
elements attached to the panels add more
architectural character to the buildings.
What was the success of the project? The
process of community engagement was very tough
during this project. The adjacent residential
neighborhood was very concerned with the outcome
of the building. After the completion of the
project, the residents were very pleased with
the design. The building was pre-leased to Tibco
Software, Inc. Biggest advantages of tilt-up for
this project was the exposed aggregate finish
and the fast construction schedule.
|